Alexander Barracks – Project Update

Alexander BarracksFollowing the success of the Elizabeth Barracks redevelopment in Pirbright, our Rollalong Defence team are currently on site developing another SLA block at neighbouring barracks, Alexander Barracks. Project Manager, Clive Harris, comments that; “The project is running ahead of schedule. We commenced groundworks in March and our first modules were delivered in May. The external brickwork is now completed two weeks ahead of programme. Internal works are progressing on programme, with bedrooms decorated and carpets laid awaiting bedroom furniture in August. Phase 2 of the groundworks have now started in preparation for utility connections in the next few weeks.”

Rollalong has an exemplary track record of working with the MoD and the project is due for completion at the beginning of October 2015.