Client: Kier Plant Limited
Project: Castlepoint
Shopping Centre, Bournemouth – temporary site office accommodation
Need: To
provide site office accommodation and welfare facilities, to service
site management and operative workers, during the construction of
the new shopping centre.
Solution: Rollalong
provided 418m2 of temporary relocatable office accommodation finished
internally to a high specification and externally finished with
Kier's own corporate livery.
In addition to the office accommodation, the building incorporates
a reception area and kitchen facilities. Rollalong also provided
portable toilets, shower and washroom facilities.
The building was manufactured in Rollalong's quality controlled
factory, including the internal fit out and installation of all
mechanical and electrical services prior to delivery to site, erection
and connection to mains services.
Duration: The building was installed in just 8 weeks.
|