Client: Turners
Facilities Management for MOD
Project: Rollestone
Dormitory Camp Accommodation
Need: Dormitory
type, basic accommodation for Armed Forces in training
Solution: Rollalong
provided a 432m2 high specification temporary accommodation
building comprising 10 bedrooms, 3 ablution areas with showers and
drying rooms, impact resistant, fully insulated walls, heavy duty
wardrobes and water sealed communal ablution areas and trickle-vented
windows, to provide Building Regulation compliance.
Rollalong incorporated a number of unique acoustic solutions to
minimise noise in the sleeping quarters. A thick layer of mineral
fibre quilt was placed in the roof which acted as sound insulation.
Rollalong overcame the problem of noisy floors by using a strengthened
steel floor structure which absorbed the noise from heavy foot traffic.
Duration: 9 weeks from Order to Hand-over
|