First Phase of Northgate School Complete

Rollalong Offsite Construction, who were appointed by West Sussex County Council to carry out a full turnkey solution to supply seven additional classrooms, new staff room, WC’s and storage areas along with an extension and redesign of staff car park. Rollalong are set for the first stage completion at Northgate Primary School in Crawley.

Despite two interruptions of snow earlier in the year and numerous storms causing site delays, the Rolla still achieved the planned Phase 1 handover, along with delivery of twenty bays of modules as programmed, completing the tarmac carpark and one classroom which links to the existing school building.

The next phase of the offsite built extension project is the completion of six KS2 classrooms. The team are working on both external and internal finishes including cladding with faced brickwork and Cedral panels to blend in with the surrounding area.

The internal finishing of the factory fitted modules continues alongside to achieve the project completion in June.